piping important concepts.


Pipe
Clearance between the outside diameter of flange and the outside diameter of pipe to the insulation should not be less than 0′- 1″* (25mm)
Clearance between the outside diameter of pipe, flange, or insulation and structural any member should not be less than 0′- 2″* (50mm)
*With full consideration of thermal movements

Platforms
Minimum width for ladder to ladder travel: 2′- 6″ (800mm)
Headroom: 7′- 0″ (2.1m)
Headroom from stairwell treads: 7′- 0″ (2.1m)
Minimum clearance around any obstruction on dead end platforms: 1′- 6″ (500mm)
Pressure Instruments 
Locate all local pressure indicators so they are visible from grade, permanent ladder, or platform. Those located less than 15 feet (4.5m) above high point of finished surface should be accessible from grade or a portable ladder. Those located in a pipeway should be considered accessible by portable ladder. Those over 15 feet (4.5m) above high point of finished surface should be accessible from a platform or permanent ladder.
Process Units
The relation of units, location of equipment, and routing of pipe should be based on economics, safety, and ease of maintenance, operation, and construction requirements. The alignment of equipment and routing of pipe should offer an organized appearance.
Process Unit Piping
Locate all pipe lines in major process units on overhead pipeways. In certain instances, pipes may be buried, providing they are adequately protected. Lines that must be run below grade, and must be periodically inspected or replaced, should be identified on the P&IDs and placed in covered concrete trenches.
Cooling water lines normally may be run above or below ground, based on economics.
Domestic or potable water and fire water lines should be run underground.
Pumps
Locate pumps close to the equipment from which they take suction. Normally, locate pumps in process units under pipeways.
Design piping to provide clearance for pump or driver removal. Similarly, on end suction pumps, piping should permit removing suction cover and pump impeller while the suction and discharge valves are in place.
Arrange suction lines to minimize offsets. The suction lines should be short and as direct as possible, and should step down from the equipment to the pump. Suction lines routed on sleeperways may rise to pump suction nozzle elevation.
Orient valve handwheels or handles so they will not interfere with pump maintenance or motor removal. Valve handwheels or handles should be readily operable from grade.
Maintenance and operating aisles with a minimum width of 2′-6″ (800mm) should be provided on three sides of all pumps.
Pump Strainers
Provide temporary conical type strainers in 2 inch (50mm) and larger butt weld pump suction lines for use during startup. Arrange piping to facilitate removal.
Use permanent Y-type strainers on 2 inch (50mm) and smaller screwed or socket weld pump suction piping.
Railroads
Headroom over through-railroads (from top rail) 22′- 6″** (7m)
Clearance from track centerline to obstruction 10′- 0″** (3m)
(** Verify conformance with local regulations)
Relief Valves (Pressure, Safety and Thermal) 
Locate all relief valves so they are accessible. Wherever feasible, locate them at platforms that are designed for other purposes. Relief valves with a centerline elevation over 15 feet (4.5m) above high point of finish surface (except in pipeways) should be accessible from platform or permanent ladder.
Pressure relief valves that discharge to a closed system should be installed higher than the collection header. There should be no pockets in the discharge line.
Safety relief valves (in services such as steam, etc.) that discharge to the atmosphere should have tail pipes extended to a minimum of 8 feet (2.5m)above the nearest operating platform that is within a radius of 25 feet (7.5m). This requirement may be waived, provided a review of the proposed arrangement indicates that it does not present a hazard. Review all pressure and safety relief valves discharging flammable vapors to the atmosphere within 100 feet (30m) of fired equipment for vapor dissipation.
Pressure and Safety relief valves, 1-1/2 inch (40mm) and larger, should only be installed with the stem and body vertical position.
Thermal relief valves, 1 inch (25mm) and smaller, may be installed with the stem and body in a horizontal position when it is impractical to install it in the vertical position.
Roads
Major process plants normally have three classes of roads. They might be called Primary roads, Secondary roads and Maintenance access ways.
Clearance or distance required
Road type Vertical Width Shoulder Side or off road Primary 21′-0″ (6.5m) 20′-0″ (6m) 5′-0″ (1.5m) 20′-0″ (6m) Secondary (*) 12′-0″ (3.7m) 12′-0″ 3.7m) 3′-0″ (1m) 10′-0″ (3m) Maintenance access 10′-0″ (3m) 10′-0″ (3m) (not req’d) 5′-0″ (1.5m)

(*) Normally secondary plant roads may be used as tube pull areas.
Safety Access
Provide a primary means of egress (continuous and unobstructed way of exit travel) from any point in any building, elevated equipment, or structure. A secondary means of escape should be provided where the travel distance from the furthest point on a platform to an exit exceeds 75 feet (25m).
Access to elevated platforms should be by permanent ladder. Safety cages should be provided on all ladders over 15′-0″ (4.5m)
The need for stairways should be determined by platform elevation, number of items requiring attention, observation and adjustment, and the frequency of items.
Ladder safety devices such as cable reel safety belts and harnesses, may be investigated for use on boiler, flare stack, water tank, and chimney ladders over 20 feet (6m) in unbroken lengths in lieu of cage protection and landing platforms.
Sample Connections
Locate all sample connections so they are readily accessible from grade or platform.
In general, where liquid samples are taken in a bottle, locate the sample outlet above a drain funnel to permit free running of the liquid before sampling.
Hot samples should be provided with a cooler.
Sleeper Pipe Supports
Normally, route piping in offsite areas on sleepers. Stagger the sleeper elevations to permit ease of crossing or change of direction at intersections. Flat turns may be used when entire sleeper ways change direction.
Spectacle Blinds
Locate spectacle blinds to be accessible from grade or platform. Blinds located in a pipeway are considered accessible. Blinds that weigh over 100 lbs (45kg) should be accessible by mobile equipment. Where this is not possible, provide davits or hitching points.
Closely grouped flanges with blinds should be staggered.
Steam Traps
Locate all steam traps at all pocketed low points and at dead ends of steam headers. Also, provide traps periodically on excessively long runs of steam piping, for sufficient condensate removal, and to ensure dry quality steam at destination. Steam traps should be accessible from grade or a platform. Steam traps located in pipeways should be considered accessible by portable ladder.
Tankage
Locate any tankage containing hydrocarbon or other combustible fluids or gasses a minimum distance of 250′-0″ (115m) from any process unit, rail loading facility or truck loading facility.
The minimum spacing of offsite storage tanks and dike requirements should be in accordance with the latest edition of the National Fire Protection Association, Code No. 30, and OSHA part 1910.106 (b), where applicable.
Temperature Instruments 
Locate temperature test wells, temperature Indicators and thermocouples to be accessible from grade or a portable ladder. Those located in a pipeway should be considered accessible by a portable ladder. Those located over 15 feet (7m) above high point of finished surface should be accessible from a platform or permanent ladder.
Locate all local temperature indicators (TI) should be visible from grade, ladder, or platform.
Towers (See Vertical Vessel)
Utility Stations
Provide and locate utility stations with water, steam, or air as indicated below:
All areas should be reachable with a single 50 foot (20m) length of hose from the station.
Provide water outlets at grade level only, in pump areas, and near equipment that should be water washed during maintenance.
Provide steam outlets at grade level only in areas subject to product spills, and near equipment that requires steaming out during maintenance.
Provide air outlets in areas where air-driven tools are used such as at exchangers, both ends of heaters, compressor area, top platform of reactors, and on columns at each manway.
Hose, hose rack, and hose connections should be provided by the client or be purchased to match the clients existing hardware.
Valve Handwheel Clearance
Clearance between the outside of hand wheel and any obstruction (knuckle clearance) should be 0′- 3″ (80mm)
Valve Operation
Locate operating valves requiring attention, observation, or adjustment during normal plant operation (noted on the P&IDs) so they may be within easy reach from grade, platform, or permanent ladder as follows:
- 2″ (50mm) and smaller may be located reachable from a ladder.
- 3″ (80mm) and larger must be reachable and operable on a platform
Operating valves with the bottom of handwheel is over 7 feet (2.1m)above high point of finished surface or operating platform may be chain-operated.
The centerline of handwheel or handles on block valves used for shutdown only, located less than 15 feet (4.5m) above high point of finished surface, and those located in pipeways, may be accessible by portable ladder.
The centerline of handwheel or handles on block valves used for shutdown only and located over 15 feet (4.5m) above high point of finished surface, except those located in pipeways, should be operable from permanent ladder or platform.
In general, keep valve handwheels, handles, and stems out of operating aisles. Where this is not practical, elevate the valve to 6′- 6″ (plus or minus 3 inches) clear from high point of finished surface to bottom of handwheel.
Vents and Drains
The P&IDs should indicate, locate and size all vents, drains, and bleeds required for process reasons and plant operation.
Provide plugged hydrostatic vents and drains without valves at the high and low points of piping.
Provide valved bleeds at control valve stations, level switches, level controllers, and gage glasses per job standard.
Vertical Vessel (Column) Piping and Platforms
Locate vertical vessels in the equipment rows on each side of the pipeway in a logical order based on the process and cost. The largest vessel in each equipment row should be used to set the centerline location of all vertical vessels in that equipment row. This largest vertical vessel should be set back from the pipe rack a distance that allows for; any pumps, the pump piping, an operation aisle between the pump piping and any piping in front of the vessel, the edge of the vessel foundation and half the diameter of this the largest vessel. Set all other vertical vessels in this same equipment row on the same centerline.
Provide a clear access area at grade for vessels with removable internals or for vessels requiring loading and unloading of catalyst or packing.
Provide vessel davits for handling items such as internals and relief valves on vessels exceeding a height of 30 feet (9m) above the high point of the finished surface, and on vessels not accessible by mobile crane. Orient davits to allow the lowering of appurtenances into the access area.
Walkways
Walkways should have a 2′-6′ (1m) horizontal clearance (not necessarily in a straight
line) and headroom of 7′- 0″ (2.1m)

Read more: http://www.egpet.net/vb/threads/4080-General-Guidelines-for-Equipment-and-Piping-Location-Spacing-Distances-and-Clearanc?s=4f812e85e1c95dc658d3d0a8855d8581#ixzz1QcZMR4SO



you may also like: MOST READ

General Guidelines for Equipment and Piping Location, Spacing, Distances and Clearances


This article should only be used as a guide. It’s intended purpose is to help the piping designer who is responsible for placement of one specific item in a typical refinery, chemical or petrochemical process plant or someone who may need help in developing a total plot plan for a complex unit.
The guidelines given here are based on my many years of experience with one of the world’s largest engineering, design and construction companies along with the U. S. OSHA Part 1910 and the NFPA (National Fire Protection Association) Code No. 30.
The latest editions of these codes and any other applicable national, regional and local codes should be referred to and used because they may be more stringent.
The subjects covered in this article have been arranged in alphabetical order in the hope it will make them easier to locate.
Access (See Maintenance)
Columns (See Vertical Vessels)
Compressors, Centrifugal
Locate centrifugal compressor as close as possible the suction source. Top suction and discharge lines either should be routed to provide clearance for overhead maintenance requirements, or should be made up with removable spool pieces.
Support piping so as to minimize dead load on compressor nozzles; the load should be within the recommended allowance of the compressor manufacturer.
Centrifugal compressors should have full platforming at operating level. Heavy parts such as upper or inner casing and rotor should be accessible to mobile equipment. Review the equipment arrangement for access and operation.
Locate lube and seal oil consoles adjacent to and as close as possible to the compressor. Oil return lines from the compressor and driver should have a minimum slope of 1/2 inch per foot to the inlet connection of seal traps, degassing tanks, and oil reservoir. Pipe the reservoir, compressor bearing, and seal oil vents to a safe location at least 6 feet above operator head level.
Compressors, Reciprocating
Locate reciprocating compressors so suction and discharge lines that are subject to vibration (mechanical and acoustical) may be routed at grade and held down at points established by a stress and analog study of the system.
Accessibility and maintenance for large lifts such as cylinder, motor rotor, and piston removal should be by mobile equipment if the installation is outdoors or by traveling overhead crane if the installation is indoors (or covered).
Horizontal, straight line, reciprocating compressors should have access to cylinder valves. Access should be from grade or platform if required.
Depending on unit size and installation height, horizontal-opposed and gas engine driven reciprocating compressors may require full platforming at the operating level.
Control Valves
Locate control valve stations accessible from grade or on a platform. In general, the (flow, level, pressure, temperature) instruments or indicators showing the process variables should be visible from the control valve.
Cooling Towers
Locate cooling towers downwind of buildings and equipment to keep spray from falling on them. Orient the short side of the tower into the prevailing summer wind for maximum efficiency. This means that the air flow (wind) will travel up the long sides and be drawn in to both sides of the cooling tower equally. When the wind is allowed to blow directly into one long side it tends to blow straight through and results in lower efficiency. Locate cooling towers a minimum of 100 feet (30m) from process units, utility units, fired equipment, and process equipment.
Cradles (See Insulation Shoes and Cradles)
Equipment Arrangement (General)
Arrange equipment, structures, and piping to permit maintenance and service by means of mobile equipment. Provide permanent facilities where maintenance by mobile equipment is impractical.
Group offsite equipment, pumps, and exchangers to permit economical pipe routing. Locate this equipment outside of diked storage areas.
Exchanger, Air Cooler (Fin Fans)
Air Coolers are in typically used in the cooling of the overhead vapor from tall vertical vessels or towers such as Crude Fractionators and Stripper Columns. The natural flow tends to follow gravity, where the tower overhead is the high point then down to the Air Cooler, then down to the Accumulator and finally the Overhead Product transfer pumps. With this in mind the Air Coolers are normally located above pipeways. This conserves plot space and allows the pipe rack structure with it’s foundation to do double duty with only minor up grade to the design. If the pipe rack is not used then plot space equal to the size of the Air Cooler is required. In addition a totally separate foundation and stand alone structure is required.
Exchanger, “G” Fin (Double Pipe)
These exchangers can be mounted almost anywhere any they can be mounted (with process engineer approval) in the vertical when required. A G-Fin Exchanger is recognizable by its shape. One segment looks like two long pieces of pipe with a 180 degree return bend at the far end. It is one finned pipe inside of another pipe with two movable supports. This type of exchanger can be joined together very simply to form multiples in series, in parallel or in a combination of series/parallel to meet the requirements of the process. This exchanger is not normally used in a service where there is a large flow rate or where high heat transfer is required. The key feature with this exchanger is the maintenance. The piping is disconnected from the tube side (inner pipe). On the return bend end of this exchanger there is a removable cover. When the cover is removed this allows for the tube (inside pipe) to be pulled out. This exchanger is normally installed with the piping connections toward the pipe rack.


Read more: http://www.egpet.net/vb/threads/4080-General-Guidelines-for-Equipment-and-Piping-Location-Spacing-Distances-and-Clearanc?s=4f812e85e1c95dc658d3d0a8855d8581#ixzz1QcYs5ba8



you may also like: MOST READ

Piping Design Engineer / Piping Design Manager

We have an Urgent Vacancy for Piping Design Engineer / Piping Design Manager in One of the Leading EPC Comapny in India.

JOB LOCATION: Delhi / Chennai

JOB PROFILE: Design Engineer-Piping / Design Manager-Piping

JOB QUALIFICATION:

B.E / B.Tech(Mechanical)
5 to 20 Years of experience in Power/Oil & Gas/Refineries/ Petrochemicals/Industrial
Knowledge of PDS,PDMS.


If your profile is matching to above requirement and If you are interested,then Please revert back along with your Updated CV along with the following Details:


Current CTC:
Expected CTC:
Notice Period:
Ready to Relocate to Delhi or Chennai??

moni@hrremedyindia.com

Thanks & Regards
Mony
HR Executive-Recruitment
HR Remedy India
Mob No: 09552564679


you may also like: MOST READ

Design Engineering Professionals

We have got urgent openings for Design Engineering Professionals in Oil & Gas and Power Sector. The openings are with one of the worlds leading EPC company based at Gurgaon.

Opening Details:

Job Location: Gurgaon

Engineers (Job openings for -Engineers – 3+ Years Exp, Senior Engineers 7+ Years Exp, Lead engineers 10+ Years Exp)

1) Civil Structural Design Engineers (Industrial Structures with 3+ Years Exp \BE\B.Tech\ME \M.Tech - Civil)
2) Electrical Design Engineers \ Instrumentation Design Engineers \ (3 to 15 Years Exp \BE\B.Tech\ME \M.Tech )
3) Static Equipment Design Engineers (3 to 15 Years Exp )
4) Rotating Equipment Design Engineers (3 to 15 Years Exp )
5) Process Design Engineers ( BE/B.Tech Chemical with Hysys or Aspen Plus or HTRI 3 to 15 Years)
6) Thermal Design Engineers
7) Materials Engineers ( Knowledge of ASME & ASTM Codes)
8) Stress & Supports Engineer

Designers (Qualification – Diploma / ITI/NCVT) (Job openings for Designers 3+Years Exp, Sr Designers 10+ Years Exp , Lead Designers 13+ Years Exp, Design Supervisors15+ Years Exp )

1) Electrical Designers \ Instrumentation Designers \ Civil Designers with SP3D or PDS or PDMS
2) Process Designers – P&ID /PFD using Microstation / SPPID

Management Professionals (Qualification – Any Engineering Degree)
Project Control Engineers, Planning & Cost Engineer 3 to 15 Years Exp, Estimation Engineers 5+ Years Exp, Procurement & Contracts Control – 5 to 15 Years
Project Management – 10+ Years Exp, Construction Management 10+ Years Exp

Interview for short listed candidates will be conducted at Gurgaon, Mumbai, Pune, Baroda, Chennai & Bangalore. Please mention your department & designation in the subject line.


If you are interested please revert back to us with your updated resume immediately and refer your friends also.



With warm Regards
Fathima / Sripradha
Executive Talent ,Acquisition
Prathmetix Consulting Group,
Chennai .
Contact number - 91-44-42868013
Mail ID - jobs@prathmetix.com
URL - www.prathmetix.com

you may also like: MOST READ

DC JOBS





you may also like: MOST READ

Job Opportunity in Hyderabad,

We have requirement matching your profile, please find the details below.

About our company
We are a high-end Engineering Solutions provider offering services ranging from Design Engineering, Process Engineering, Reverse Engineering, Product Data Management (PDM), Knowledge Based Engineering and Software Customization. With sales and marketing offices located in United States, UK, Germany, Japan, Australia, and Canada, A global player in the Engineering Services Sector focused on the Automotive Industry. 

Job Location – Hyderabad
Experience – 3 to 6 years.

Desired Profile.

Should have worked in Automotive domain
Should have good hands on experience in CATIA

Education - B.E. / B.Tech 
Language Requirements
Essential: English

If interested, request you to kindly forward your updated RESUME immediately.

Disclaimer – This is a mass-mailer, kindly ignore if your profile doesn’t match our requirement.

With best regards,
Gopi.T.K
+91 95000 94188


 


you may also like: MOST READ

PDS, Micro Station,Autocad,GIS jobs


EDI_GIS or Gentran intigration suits
HCL Technologies - Hyderabad, Andhra Pradesh
Hi, This is Minati from HCL Technoloigies.We are hiring GIS professionals. Skill : EDI With GIS Experience : 4 years to 8 years Job location : Hyderabad If... 
From Monster IN - 9:42 PM - save job, email, block, more...
 

Field Surveyor
Team Lease - Hyderabad, Andhra Pradesh
graduates or undergraduates are eligibile.Candidate will be given training on GIS Autocad and other instruments by the company.Salary would be 10000.Average... 
From TimesJobs.com - 1:32 AM - save job, email, block, more...
 

C/C++ Consultant
Hyderabad, Andhra Pradesh
Information Systems (GIS), and IT services. We... Utilities. Designation C/C++ Consultant - 1 Opening(s) Hiring ForInfotech Job Description Job... 
From Naukri.com - 11:22 PM - save job, email, block, more...
 

Junior / Senior Quality Process Analyst
Hyderabad, Andhra Pradesh
Engineering Services, Geographic Information Systems (GIS), and IT services. We provide services to a wide... Process Analyst - 3 Opening(s) Job Description Role... 
From Naukri.com - 11:22 PM - save job, email, block, more...
 

Jeltron Systems (India) Pvt. Ltd.
Jeltron Systems (India) Pvt. Ltd. - Hyderabad, Andhra Pradesh
Flair for Marketing is plus. Autocad Engineers: Mechanical/ Electrical Diploma holders with some experience in AutoCAD and Panel designing. Accountant: B.Com... 
From CareerAge.com - 10:05 PM - save job, email, block, more...
 

Product Engineer
Elixir Web Solutions Pvt. Ltd - Hyderabad, Andhra Pradesh
etc.,) &bull Proficiency design software including Pro-E Solid Works and AutoCAD &bull Able to perform and analyze results from FEA &bull Working knowledge in... 
From SpanJobs.com - 6:50 PM - save job, email, block, more...
 

Product Engineer
Elixir Web Solutions - Hyderabad, Andhra Pradesh
graphs, etc... Proficiency design software including Pro-E Solid Works and AutoCAD · Able to perform and analyze results from FEA · Working knowledge... 
From Monster IN - 1:16 PM - save job, email, block, more...
 

Product Engineer
Elixir Web Solutions Pvt. Ltd, hiring for A US based manufacturer of electrical & communication components -Hyderabad, Andhra Pradesh
graphs, etc... Proficiency design software including Pro-E Solid Works and AutoCAD • Able to perform and analyze results from FEA • Working knowledge in... 
From Naukri.com - 6:30 PM - save job, email, block, more...
 


you may also like: MOST READ

saudi jobs



MECHANICAL SUPERVISOR-JIT-3/09 (7-9 yrs )

Company : Jal International (Sabic Group)
Qualification : BE / B.Tech
Job Location : SAUDI ARABIAApply to this Job



ROTATING SUPERVISOR -JIT-3/09 (7-9 yrs )

Company : Jal International (Sabic Group)
Qualification : BE / B.Tech
Job Location : SAUDI ARABIAApply to this Job



Foreman Floating Dock -QTG-2/09 (5-7 yrs )

Company : Qatar Navigation Qsc
Qualification : I.T.I., 10th
Job Location : QATARApply to this Job



ENGINEER-AIR CONDITIONING & REFRIGERATION-EFC-2/09 (5-10 yrs )

Company : Emirates Flight Catering(EKFC)
Qualification : BE / B.Tech
Job Location : DubaiApply to this Job



ENGINEER -REFRIGERATION -EFC-2/09 (5-10 yrs )

Company : Emirates Flight Catering(EKFC)
Qualification : BE / B.Tech
Job Location : DubaiApply to this Job



ROTATING ENGINEER-JIT-3/09 (7-9 yrs )

Company : Jal International (Sabic Group)
Qualification : BE / B.Tech
Job Location : SAUDI ARABIAApply to this Job



Mechanical Auto Cadd Draftsman -AFL-2/09 (5-7 yrs )

Company : Arabian Fal Company
Qualification : Diploma, I.T.I.
Job Location : SAUDI ARABIAApply to this Job



Scaffolding Foreman -AFL-2/09 (7-10 yrs )

Company : Arabian Fal Company
Qualification : Diploma
Job Location : SAUDI ARABIAApply to this Job



Plant Supervisor -AFL-2/09 (5-8 yrs )

Company : Arabian Fal Company
Qualification : Diploma
Job Location : SAUDI ARABIAApply to this Job



Automobile Engineer -AFL-2/09 (7-10 yrs )

Company : Arabian Fal Company
Qualification : BE / B.Tech
Job Location : SAUDI ARABIAApply to this Job


you may also like: MOST READ

software and other jobs



RoleCompanyLocation
Oracle SCM Functional ConsultantA Client of Infokall Enterprise Solutions LtdHyderabadApply

ASP.Net Tech LeadA Client of Infokall Enterprise Solutions LtdChennaiApply

Factory In-ChargeA client of ABC INTERNATIONALMultiple LocationApply

Project Manager/ Project LeaderAegis LimitedChennaiApply


you may also like: MOST READ

PIPING JOBS


Structural Design Engineer
A Client Of Alps HR Consultants Pvt Ltd - Delhi
Structural Design Engineer Noida/ Greater Noida Qualification: Graduation - BE/B.Tech, Diploma (Civil... in our industry 2. PDS / PDMS Modellers with 5 to 20...
From Shine.com - 11:46 PM - save job, email, block, more...


LTC-Design Engineer- Electrical
Mumbai, Maharashtra
notch engineers Designation LTC-Design Engineer... Infrastructure/Energy Role Design Engineer Functional Area Engineering Design, R&D Education...
From Naukri.com - 6:29 PM - save job, email, block, more...


Dy. Chief Engineer / Chief Engineer
Mangalam Placements Pvt Ltd, hiring for A reputed client of Mangalam Placements Pvt Ltd - Pune, Maharashtra
CSA Engineer & Designers. Manpower Planning. Keywords: Chief Engineer, Analysis, Design, RCC, Steel, Lead Egnieer, RCC, Steel Structures, STAAD, 3D, PDS...
From Naukri.com - 11:21 PM - save job, email, block, more...


Principal Engineer – Piping Layout
Naman Integrated Management Services Pvt. Ltd. - Kolkata, West Bengal
Candidate Profile  13-20 years in Piping Layout Design for Refinery, Petrochemical, Chemical or related... quality engineering and design services to process...
From Naukri.com - 6:30 PM - save job, email, block, more...


Junior / Senior Engineer - Highway
Bangalore, Karnataka
Engineer include, but are not limited to:  Design... junction design standards-using PDS as design tool  Familiarity with typical UK local authority design...
From Naukri.com - 6:25 PM - save job, email, block, more...


Instrumentation Engineer - Process plant, Oil&Gas
Mangalam Placements Pvt Ltd, hiring for A reputed client of Mangalam Placements Pvt Ltd - Pune, Maharashtra
of 3D PDMS/PDS software/IN tools/instrument sizing will have plus edge. Exp : 7 to 18 yrs Job Description Hands of experience on design/detail engineering...
From Naukri.com - 11:21 PM - save job, email, block, more...


INSTRUMENT DESIGNER / SENIOR INSTRUMENTATION DESIGNER
Brunel India Pvt Ltd - Chennai, Tamil Nadu
with Instrumentation design, as applicable. Knowledge of software’s like PDMS / PDS/ AutoCAD / Micro... SPI) software prepare design documentation required...
From Naukri.com - 11:21 PM - save job, email, block, more...


ELECTRICAL DESIGNER / SENIOR ELECTRICAL DESIGNER
Brunel India Pvt Ltd - Chennai, Tamil Nadu
design. Knowledge of software like PDMS / PDS... by engineers Draw/update Lighting, small power, grounding, layouts, Nav Aid layout Lighting design...
From Naukri.com - 11:29 PM - save job, email, block, more...



you may also like: MOST READ